I'm having difficulty with a small program I'm writing dealing with
dates. I've written the calendar class below. It works just fine
when calling getMonth for all months EXCEPT NOVEMBER. Interrupting
the call while in irb shows that it is busy in the reduce method of
Rational, called from Date. Any ideas?
Thanks,
Russ
require 'date'
class Calendar
def initialize(year=Date.today.year) @year = year
end
def getMonth(mo)
dt = Date.new(@year, mo, 1)
i = dt.month
list = Array.new
while i != (mo+1) % 12
wk = getWeek(dt.month, dt.day)
dt = wk[6].succ
i = dt.month
list.push(wk)
end
list
end
def getWeek(mo, dy)
dt = Date.new(@year, mo, dy)
dt -= dt.wday
list = Array.new
for i in 0..6
list.push dt
dt = dt.succ
end
list
end
def getDay(mo, dy)
Date.new(@year, mo, dy)
end
end
I'm having difficulty with a small program I'm writing dealing with
dates. I've written the calendar class below. It works just fine
when calling getMonth for all months EXCEPT NOVEMBER. Interrupting
the call while in irb shows that it is busy in the reduce method of
Rational, called from Date. Any ideas?
(...)
def getMonth(mo)
dt = Date.new(@year, mo, 1)
i = dt.month
list = Array.new
while i != (mo+1) % 12
wk = getWeek(dt.month, dt.day)
dt = wk[6].succ
i = dt.month
list.push(wk)
end
list
end
(...)
Russ, for November, "mo" is 11, and "(mo+1) % 12" is zero, but "dt.month" and "i" are always in the range (1..12), so you've got an endless loop. Replace the line
I'm having difficulty with a small program I'm writing dealing with
dates. I've written the calendar class below. It works just fine
when calling getMonth for all months EXCEPT NOVEMBER. Interrupting
the call while in irb shows that it is busy in the reduce method of
Rational, called from Date. Any ideas?
(...)
def getMonth(mo)
dt = Date.new(@year, mo, 1)
i = dt.month
list = Array.new
while i != (mo+1) % 12
wk = getWeek(dt.month, dt.day)
dt = wk[6].succ
i = dt.month
list.push(wk)
end
list
end
(...)
Russ, for November, "mo" is 11, and "(mo+1) % 12" is zero, but
"dt.month" and "i" are always in the range (1..12), so you've got an
endless loop. Replace the line
while i != (mo+1) % 12
with
next_month = mo % 12 + 1
while i != next_month
and at least the loop should work as you expect.
Regards,
Pit
Pit,
Thank-you very much. Can't believe I didn't see that mistake.
Any idea why ruby's date class needs to use rational numbers, though?
Every time I'd get into the loop and break out in irb, I'd see a stack
trace pointing to rational.rb...
Because the Date is stored as Astronomical Julian Date number
(whatever it is, see lib/date.rb comments and source) and the
conversion somehow needs it. NB: Due to this, I obtained a decent
speedup by caching Date object instead of creating them each time
anew.
···
On 8/15/06, Russ Pridemore <russ.pridemore@gmail.com> wrote:
Any idea why ruby's date class needs to use rational numbers, though?
Every time I'd get into the loop and break out in irb, I'd see a stack
trace pointing to rational.rb...